9.2.17 Update: Jaycee Park is completed and open for play.
8.16.17 Update:
 Grass seed has been planted and is currently being irrigated daily in order to grow. Basketball goals are to be installed. The park will open late summer 2018. 
7.6.17 Update:
 The trail has been completed and the splash pad and basketball courts have been painted. Picnic tables have been placed under the pavilions. A tentative date of mid to late August has been set for reopening. 
4.13.17 Update:
Construction of the splash pad is underway. 
2.22.17 Update:
 Construction of the playground and trail is underway. The pergolas and pavilion have been installed. The Splash Pad is currently being manufactured. 
11.9.16 Update: The following items will be awarded at the 11/17/16 City Council Meeting: Trail, Exercise Stations, Pergolas, Benches, Pavilion, Sport Court Work and Renovations to the Existing Parking Lot. The playground has been ordered and is estimated to be installed in January 2017. The Department is currently reviewing different Splash Pad designs.
12.7.16 Update - Park will feature a space themed Splash Pad to compliment the current "rocket" play structure.